Non-Compliance detail


  
Summary
 
Licence number: 2094
Annual Return Start: 30 Jun 2020
Annual Return End: 29 Jun 2021
Date Received: 25 Aug 2021
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M9.1 Monitoring Point 6 (HRSTS discharge point) failed to monitor turbidity continuously during discharge in accordance with Condition M2.3 due to equipment error. Appropriate Action taken by licensee 1
M2.2 Monitoring Point 9 (SX38-D3) failed to monitor PM10 continuously in accordance with Condition M2.2 during the reporting period due to equipment malfunction or planned maintenance activities. Appropriate Action taken by licensee 18
M2.2 Monitoring Point 10 (SX38-D4) failed to monitor PM10 continuously in accordance with Condition M2.2 during the reporting period due to equipment malfunction or planned maintenance activities. Appropriate Action taken by licensee 10
M2.2 Monitoring Point 11 (SX38-D5) failed to monitor PM10 continuously in accordance with Condition M2.2 during the reporting period due to equipment malfunction or planned maintenance activities. Appropriate Action taken by licensee 13
M2.2 Monitoring Point 12 (SX38-D6) failed to monitor PM10 continuously in accordance with Condition M2.2 during the reporting period due to equipment malfunction or planned maintenance activities. Appropriate Action taken by licensee 11
O5.1 The in pit disposal of heavy plant tyre waste did not meet Condition O5.1 b on five occasions whereby the maximum of 10 tyres per site/stack was exceeded Appropriate Action taken by licensee 5